Difficulty: Medium
Correct Answer: Develop Project Charter and Identify Stakeholders
Explanation:
Introduction / Context:
The PMBOK Guide organizes individual processes into process groups, and each process group contains specific processes that serve a particular purpose in the project life cycle. The Initiating Process Group focuses on authorizing the project or phase and identifying key players. Knowing which processes belong to Initiating is important for both the exam and real world planning of when to perform each activity. This question asks you to recognize the pair of processes that correctly belongs to the Initiating Process Group.
Given Data / Assumptions:
Concept / Approach:
Initiating processes ensure that there is a clear project charter and that stakeholders are identified at a high level. Develop Project Charter formally authorizes the project and gives the project manager authority to use organizational resources. Identify Stakeholders identifies everyone who might affect or be affected by the project. Processes like Develop Project Management Plan, Create WBS, Direct and Manage Project Execution, Perform Integrated Change Control and Close Project or Phase belong to other groups. The key to answering the question is associating each named process with its correct process group and selecting the pair that both belong to Initiating.
Step-by-Step Solution:
Step 1: Recall that Develop Project Charter is an Initiating process used to create and approve the charter.Step 2: Recall that Identify Stakeholders, in modern PMBOK editions, is also part of the Initiating Process Group because it happens very early to set expectations and plan communications.Step 3: Look at option A, which pairs Develop Project Charter with Identify Stakeholders. This is consistent with the framework.Step 4: Review option B. Develop Project Management Plan and Create WBS are planning processes, not initiating.Step 5: Examine option C. Direct and Manage Project Execution and Perform Integrated Change Control are executing and monitoring and controlling processes respectively.Step 6: Consider option D. Close Project or Phase and Close Procurements belong to the Closing Process Group.Step 7: Conclude that option A is the only pair that correctly represents Initiating processes.
Verification / Alternative check:
If you check a standard PMBOK process group table, you will see Develop Project Charter and Identify Stakeholders aligned under the Initiating Process Group in the Integration and Stakeholder Management knowledge areas. All other processes listed in the options appear in different groups. This cross reference confirms that the pairing in option A is correct.
Why Other Options Are Wrong:
Option B lists planning activities where detailed scope and plan development occur, which happen after Initiating. Option C contains execution and change control processes that take place after planning and initial authorization. Option D lists closing activities that finalize the project or phase and deal with contracts, clearly not part of Initiating. These options are useful distractors but do not match the group the question asks about.
Common Pitfalls:
One common mistake is to group processes by when they sound like they occur rather than where the PMBOK places them. For example, some candidates think Identify Stakeholders belongs to Planning because detailed stakeholder analysis happens there. Another pitfall is to assume that all integration processes are in the same group, when in fact Integration touches multiple process groups. Carefully memorizing which processes belong to each group will help avoid such confusion.
Final Answer:
The processes correctly associated with the Initiating Process Group are Develop Project Charter and Identify Stakeholders.