Within the Closing Process Group, which processes are typically included to formally complete the project or phase?

Difficulty: Easy

Correct Answer: Close Project or Phase and Close Procurements

Explanation:


Introduction / Context:
The Closing Process Group finalizes all activities across all project management process groups to formally complete the project or phase. It ensures that deliverables are accepted, contracts are closed and organizational process assets are updated with lessons learned. Knowing which processes belong to the Closing group helps you plan for orderly project completion and exam questions that ask about closing tasks. This question focuses on recognizing the closing processes in a multiple choice format.


Given Data / Assumptions:

  • The PMBOK Guide describes a small number of processes in the Closing Process Group.
  • Close Project or Phase and Close Procurements are classic closing processes in many PMBOK editions.
  • Other listed processes belong to Initiating, Executing or Monitoring and Controlling groups.
  • You must choose which pair correctly represents closing activities.


Concept / Approach:
Close Project or Phase finalizes all activities for the project or a specific phase, confirms acceptance of deliverables and updates organizational process assets. Close Procurements completes each project procurement, settles claims and closes contracts. Together they represent key closing work. Develop Project Charter and Identify Stakeholders belong to Initiating, Direct and Manage Project Execution and Perform Quality Assurance belong to Executing, and Monitor and Control Project Work and Perform Integrated Change Control are monitoring and controlling processes. By associating each process with its group, you can quickly identify the closing pair.


Step-by-Step Solution:
Step 1: Recall that Close Project or Phase is explicitly named as a Closing Process Group activity in Integration Management.Step 2: Recall that Close Procurements is a procurement related closing process used to complete and settle contracts.Step 3: Examine option A, which pairs Close Project or Phase with Close Procurements. This correctly reflects the closing focus.Step 4: Review option B. Develop Project Charter and Identify Stakeholders are initiating processes that occur at the start of a project.Step 5: Review option C. Direct and Manage Project Execution and Perform Quality Assurance are executing processes.Step 6: Review option D. Monitor and Control Project Work and Perform Integrated Change Control are monitoring and controlling processes.Step 7: Conclude that option A is the only one that lists closing processes.


Verification / Alternative check:
Open a PMBOK process chart and verify that Close Project or Phase appears under the Closing Process Group in Project Integration Management, and Close Procurements appears under the Closing group in Procurement Management. The absence of other processes in the Closing group confirms that these are indeed the key closing processes in many exam frameworks. This matches option A exactly.


Why Other Options Are Wrong:
Option B contains initiation processes focused on authorization and early stakeholder identification, not closure. Option C includes execution processes that deal with performing and assuring the work. Option D lists monitoring and controlling activities that regulate performance and manage changes throughout the project rather than finalizing it. None of these deliver the formal completion and administrative closure that Closing requires.


Common Pitfalls:
Some candidates overlook the importance of closing activities, focusing only on planning and execution. They may forget tasks such as confirming acceptance, archiving records and releasing resources. Another pitfall is confusing contract closure with administrative project closure; exams may test whether you recognize that both are needed. Remember that properly closing a project or phase protects the organization from legal and financial risk and captures lessons for future work.


Final Answer:
The processes typically included in the Closing Process Group are Close Project or Phase and Close Procurements.