The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
Options
A. 19
B. 14
C. 24
D. None of these.
Correct Answer
19
Construction Management problems
Search Results
1. Pick up the correct statement from the following:
Options
A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
C. The float which affects neither the processor nor the successor activities, is called independent float
D. The difference between total float and free float, is called interfering float
2. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
Options
A. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
B. Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity
C. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
D. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time