logo

CuriousTab

CuriousTab

Discussion


Home Civil Engineering Construction Management Comments

  • Question
  • The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
    The three time estimates for the activities of the network shown in the given figure are shown above


  • Options
  • A. 19
  • B. 14
  • C. 24
  • D. None of these.

  • Correct Answer
  • 19 


  • Construction Management problems


    Search Results


    • 1. Pick up the correct statement from the following:

    • Options
    • A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
    • B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
    • C. The float which affects neither the processor nor the successor activities, is called independent float
    • D. The difference between total float and free float, is called interfering float
    • E. All the above.
    • Discuss
    • 2. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

    • Options
    • A. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
    • B. Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity
    • C. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
    • D. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
    • E. All the above.
    • Discuss
    • 3. Pick up the correct statement from the following:

    • Options
    • A. Optimistic time estimate refers to activities
    • B. Pessimistic time estimate refers to activities
    • C. Most likely time estimate refers to activities
    • D. Expected time estimate refers to activities
    • E. All the above.
    • Discuss
    • 4. Pick up the correct statement from the following:

    • Options
    • A. Programme Evaluation and Review Technique, is event oriented
    • B. Programme Evaluation and Review Technique is not event oriented
    • C. Critical Path Method is event oriented
    • D. Critical Path method is event oriented.
    • Discuss
    • 5. The first stage of a construction, is

    • Options
    • A. preparation of estimate
    • B. survey of the site
    • C. initiation of proposal
    • D. preparation of tender
    • E. allotment of funds.
    • Discuss
    • 6. Pick up the correct statement from the following:

    • Options
    • A. Earliest expected time is denoted by TE
    • B. Latest occurrence time is denoted by TL
    • C. Contractual obligation time is denoted by Ts
    • D. Latest occurrence time is taken as contractual obligation time
    • E. All the above.
    • Discuss
    • 7. PERT is

    • Options
    • A. an analytic in concept
    • B. limited of event oriented diagrams
    • C. used for research and development projects
    • D. based on three time estimates for activities linking up two events
    • E. all the above.
    • Discuss
    • 8. A goiden rule for the procurement of construction stones, suggests

    • Options
    • A. 100% at the site
    • B. 67% at the site and 33% under procurement
    • C. 50% at the site and 50% under procurement
    • D. 33% at the site and 67% under procurement
    • E. none of these.
    • Discuss
    • 9. Which one of the following represents an event?

    • Options
    • A. concrete cured
    • B. fixing of door
    • C. plastering of walls
    • D. selecting sites
    • E. all the above.
    • Discuss
    • 10. For the execution of a project, a contractor is

    • Options
    • A. a person
    • B. a firm
    • C. an agency
    • D. all the above.
    • Discuss


    Comments

    There are no comments.

Enter a new Comment