Difficulty: Easy
Correct Answer: 8 days
Explanation:
Introduction / Context:Problems with an initial solo day followed by joint work are solved by subtracting the first day’s contribution and then dividing the remainder by the combined daily rate.
Given Data / Assumptions:
Concept / Approach:Remaining fraction = 1 − 1/15. Combined rate = 1/15 + 1/20.
Step-by-Step Solution:
After day 1 by A: completed = 1/15; remaining = 14/15Joint rate = 1/15 + 1/20 = (4 + 3)/60 = 7/60 per dayDays needed = (14/15) / (7/60) = (14/15) * (60/7) = 8 daysVerification / Alternative check:Total time = 1 + 8 = 9 days; check: 9 * (1/15) + 8 * (1/20) = 0.6 + 0.4 = 1 job.
Why Other Options Are Wrong:7 or 6 days leave unfinished work; “None of these” is unnecessary because 8 is exact.
Common Pitfalls:Forgetting that the question asks for additional days after the first solo day.
Final Answer:8 days
Discussion & Comments