Difficulty: Easy
Correct Answer: 8 days
Explanation:
Introduction / Context:
Problems with an initial solo day followed by joint work are solved by subtracting the first day’s contribution and then dividing the remainder by the combined daily rate.
Given Data / Assumptions:
Concept / Approach:
Remaining fraction = 1 − 1/15. Combined rate = 1/15 + 1/20.
Step-by-Step Solution:
Verification / Alternative check:
Total time = 1 + 8 = 9 days; check: 9 * (1/15) + 8 * (1/20) = 0.6 + 0.4 = 1 job.
Why Other Options Are Wrong:
7 or 6 days leave unfinished work; “None of these” is unnecessary because 8 is exact.
Common Pitfalls:
Forgetting that the question asks for additional days after the first solo day.
Final Answer:
8 days
Discussion & Comments