Difficulty: Medium
Correct Answer: None of these
Explanation:
Introduction / Context:
This is a classic manpower–time problem with a change in crew size mid-project. We translate total work into person-days, account for work already done, and then compute the duration for the remainder with the increased team.
Given Data / Assumptions:
Concept / Approach:
Compute the total work in person-days. Subtract the contribution of the first phase (already completed). Divide leftover person-days by the new team size to get the additional days required after the joining event.
Step-by-Step Solution:
Verification / Alternative check:
Total elapsed time from the start would be 12 + 8 = 20 days. The question specifically asks for the time to complete the remaining work after the join, which is 8 days. Since 8 days is not among the listed numeric options, the correct choice is “None of these.”
Why Other Options Are Wrong:
12 days: Ignores increased manpower; would overshoot.
7 days: Underestimates the remaining person-days for 16 workers.
9 days: Overestimates remainder time compared with exact division (128/16).
Common Pitfalls:
Confusing total duration with post-joining duration; not converting to person-days; or rounding prematurely. Always calculate remainder precisely.
Final Answer:
None of these (the required time for the remainder is 8 days)
Discussion & Comments