Difficulty: Medium
Correct Answer: None of these
Explanation:
Introduction / Context:
The original stem was broken. By the Recovery-First Policy, we minimally repair it to reflect a common variant: C’s solo time is four-fifths of the joint time of A and B. We then compute how long C needs to finish after A and B have worked some initial days.
Given Data / Assumptions:
Concept / Approach:
Compute initial work by A and B, find the leftover fraction, then divide by C’s rate.
Step-by-Step Solution:
Verification / Alternative check:
Multiply C’s rate by 36/25: (25/96)*(36/25) = 36/96 = 3/8, which matches the remainder.
Why Other Options Are Wrong:
8, 6, 3 are far from 1.44 days; the only valid choice is “None of these.”
Common Pitfalls:
Interpreting “four-fifths” against A or B instead of the joint A+B time; or adding times rather than rates.
Final Answer:
None of these
Discussion & Comments