Difficulty: Medium
Correct Answer: 05:11 p.m.
Explanation:
Introduction / Context:
Time-and-work problems often require converting individual times to rates, adding rates for simultaneous work, and then tracking partial progress across phases. Here, three typists start together; one leaves after 4 hours, and the others finish. We must compute the exact finish time from the start at 9:00 a.m.
Given Data / Assumptions:
Concept / Approach:
Use unit-work method. Total work W = 1 report. Sum rates when people work together; multiply by time to get completed fraction. Remainder divided by the later combined rate gives the additional time needed.
Step-by-Step Solution:
Verification / Alternative check:
As a quick reasonableness check, A contributes 4*(1/16)=1/4. B and C together at 11/120 per hour need about (3/4)/(11/120) ≈ 8.18 hours if A never came; but A contributed more than 1/4 because everyone worked initially; our precise arithmetic above gives 5:11 p.m., which is consistent.
Why Other Options Are Wrong:
04:10 p.m.: underestimates remaining time after A leaves.
05:45 p.m.: overestimates B+C time.
06:15 p.m.: significantly longer than required by computed remainder and rate.
Common Pitfalls:
Mixing average time with sum of times; not converting to per-hour rates; rounding too early; or assuming integer minutes. Keep exact fractions until the end.
Final Answer:
05:11 p.m.
Discussion & Comments