5 persons can prepare an admission list in 8 days working 7 hours a day. If 2 persons join them so as to complete the work in 4 days, they need to work per day for
Aptitude
Time and Work
Difficulty: Medium
Choose an option
-
A8 hours
-
B9 hours
-
C10 hours
-
D12 hours
Answer
Correct Answer: 10 hours
Explanation
### Concept & Work Equivalence Formula
The total man-hours required for a fixed task remain constant:
$$ M_1 \times D_1 \times H_1 = M_2 \times D_2 \times H_2 $$
### Step-by-Step Solution
* **Given**:
- $M_1 = 5$, $D_1 = 8$, $H_1 = 7$
- After $2$ persons join, $M_2 = 5 + 2 = 7$
- Target days: $D_2 = 4$
- Required hours per day: $H_2 = x$
* **Calculation**:
$$ 5 \times 8 \times 7 = 7 \times 4 \times x $$
$$ 280 = 28x $$
$$ x = \frac{280}{28} = 10 $$
### Exam Strategy & Shortcut
Cancel $7$ from both sides immediately: $5 \times 8 = 4 \times x \implies 40 = 4x \implies x = 10$.
### Common Pitfall
Forgetting to update the number of persons by adding the $2$ new workers, using $5$ instead of $7$ for $M_2$.
### Final Answer
Therefore, the correct answer is **10 hours**.