A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job?
Aptitude
Time and Work
Difficulty: Hard
Choose an option
-
A8 days
-
B9 days
-
C10 days
-
D12 days
Answer
Correct Answer: 9 days
Explanation
### Concept & Rate of Work
This problem connects total work, rate of work, and time taken.
$$ \text{Total Work} = \text{Rate} \times \text{Time} $$
If the total work is constant, an increase in the rate results in a decrease in time.
### Step-by-Step Solution
* **Variables:** Let the originally planned number of days be $x$. The total pieces to be made is 360.
* **Planned Rate:** The planned number of pieces per day is $\frac{360}{x}$.
* **Actual Scenario:** They made 4 more pieces per day, so the actual rate is $\frac{360}{x} + 4$. They finished a day ahead of schedule, so the actual time taken is $x - 1$ days.
* **Equation:** The total work is the product of actual rate and actual time.
* $(\frac{360}{x} + 4)(x - 1) = 360$
* $360 - \frac{360}{x} + 4x - 4 = 360$
* $4x - \frac{360}{x} - 4 = 0$
* Divide by 4: $x - \frac{90}{x} - 1 = 0$
* Multiply by $x$: $x^2 - x - 90 = 0$
* **Factorize:** $(x - 10)(x + 9) = 0$. Since days cannot be negative, $x = 10$.
* **Final Step:** The planned number of days was 10. The question asks how many days they *did* take (actual time), which is $10 - 1 = 9$ days.
### Exam Strategy & Shortcut
Use option elimination on the actual days taken. If actual days = 9 (Option B), then planned days = 10.
Planned rate = $360 / 10 = 36$. Actual rate = $360 / 9 = 40$.
Difference in rate = $40 - 36 = 4$. This matches the condition "four more pieces per day". Option B is correct.
### Common Pitfall
A major pitfall is solving the quadratic equation for $x$ (which gives 10) and selecting 10 as the answer, forgetting that $x$ is the *planned* time, but the question asks for the *actual* time taken ($x - 1$).
### Final Answer
Therefore, the correct answer is **9 days**.