X can do $\frac{1}{4}$ of a work in 10 days, Y can do 40% of the work in 40 days and Z can do $\frac{1}{3}$ of the work in 13 days. Who will complete the work first ?
Aptitude
Time and Work
Difficulty: Medium
Choose an option
-
AX
-
BY
-
CZ
-
DX and Z both
Answer
Correct Answer: Z
Explanation
### Concept & Strategy
To find out who completes the work first, calculate the total time each person takes to complete 100% (or $1$ whole) of the work. The person who takes the minimum total time will complete the work first.
### Step-by-Step Solution
* **Time taken by X:**
X completes $\frac{1}{4}$ of the work in $10$ days.
Time taken to complete the whole work = $10 \times 4 = 40$ days.
* **Time taken by Y:**
Y completes $40\%$ ($\frac{40}{100}$ or $\frac{2}{5}$) of the work in $40$ days.
Time taken to complete the whole work = $40 \times \frac{5}{2} = 100$ days.
* **Time taken by Z:**
Z completes $\frac{1}{3}$ of the work in $13$ days.
Time taken to complete the whole work = $13 \times 3 = 39$ days.
* **Comparison:**
Comparing the total times ($40$ days, $100$ days, $39$ days), Z takes the least number of days ($39$ days).
### Exam Strategy & Shortcut
Rather than finding full work times, you can quickly estimate their pace to find the fastest worker:
X does $25\%$ in $10$ days -> $100\%$ in $40$ days.
Y does $40\%$ in $40$ days -> very slow.
Z does $33.33\%$ in $13$ days -> $100\%$ in $39$ days.
Clearly, Z is the fastest.
### Common Pitfall
A common mistake is directly comparing the given days ($10$, $40$, $13$) without adjusting for the fraction of work completed, which leads to incorrectly choosing X.
### Final Answer
Therefore, the correct answer is **Z**.