Ayesha can complete a piece of work in 16 days. Amita can complete the same piece of work in 8 days. If both of them work together in how many days can they complete the same piece of work?
Aptitude
Time and Work
Difficulty: Easy
Choose an option
-
A$4\frac{2}{5}$ days
-
B$5\frac{1}{3}$ days
-
C6 days
-
D12 days
-
ENone of these
Answer
Correct Answer: $5\frac{1}{3}$ days
Explanation
### Concept & Time and Work
The rate of work is inversely proportional to the time taken. If a person can complete a work in $n$ days, their 1-day work is $\frac{1}{n}$. When working together, their combined 1-day work is the sum of their individual 1-day works.
### Step-by-Step Solution
* **Given:**
Ayesha takes 16 days to complete the work.
Amita takes 8 days to complete the work.
* **Calculation:**
Ayesha's 1-day work = $\frac{1}{16}$
Amita's 1-day work = $\frac{1}{8}$
Combined 1-day work = $\frac{1}{16} + \frac{1}{8}$
To add the fractions, find a common denominator (which is 16):
Combined 1-day work = $\frac{1}{16} + \frac{2}{16} = \frac{3}{16}$
* Therefore, the time taken to complete the work together is the reciprocal of their combined 1-day work, which is $\frac{16}{3}$ days.
* Converting $\frac{16}{3}$ to a mixed fraction:
$16 \div 3 = 5$ with a remainder of 1.
So, $\frac{16}{3} = 5\frac{1}{3}$ days.
### Exam Strategy & Shortcut
Use the LCM (Total Work) method. Let Total Work = LCM of (16, 8) = 16 units.
Ayesha's efficiency = 16 / 16 = 1 unit/day.
Amita's efficiency = 16 / 8 = 2 units/day.
Combined efficiency = 1 + 2 = 3 units/day.
Total time = Total Work / Combined efficiency = 16 / 3 = $5\frac{1}{3}$ days.
### Common Pitfall
A common mistake is simply averaging the days (e.g., $(16+8)/2 = 12$ days). Remember that working together always takes less time than the fastest individual.
### Final Answer
Therefore, the correct answer is **$5\frac{1}{3}$ days**.