P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ?

Aptitude Time and Work Difficulty: Medium
Choose an option
  • A
    $5 \frac{5}{11}$
  • B
    $5 \frac{6}{11}$
  • C
    $6 \frac{5}{11}$
  • D
    $6 \frac{6}{11}$
  • E
    None of these

Answer

Correct Answer: $5 \frac{5}{11}$

Explanation

### Concept & Formula / Logic To compare work done by individuals with varying daily hours, it is necessary to convert their total work time into a single standard unit, typically total hours. $$ \text{Total Hours} = \text{Number of Days} \times \text{Hours per Day} $$ ### Step-by-Step Solution 1. **Calculate total hours for P:** P completes the work in 12 days, working 8 hours a day. Total hours for P = $12 \times 8 = 96 \text{ hours}$. P's 1-hour work rate = $\frac{1}{96}$. 2. **Calculate total hours for Q:** Q completes the same work in 8 days, working 10 hours a day. Total hours for Q = $8 \times 10 = 80 \text{ hours}$. Q's 1-hour work rate = $\frac{1}{80}$. 3. **Calculate combined work rate per hour:** (P + Q)'s 1-hour work = $\frac{1}{96} + \frac{1}{80}$ To add the fractions, find the LCM of 96 and 80, which is 480. $\frac{5}{480} + \frac{6}{480} = \frac{11}{480}$ This means working together, they can finish the work in $\frac{480}{11}$ total hours. 4. **Calculate total days when working 8 hours a day:** Number of days = $\frac{\text{Total Hours Required}}{\text{Hours per Day}}$ Number of days = $\frac{\frac{480}{11}}{8} = \frac{480}{11 \times 8} = \frac{60}{11}$ days. Convert to a mixed fraction: $\frac{60}{11} = 5 \frac{5}{11}$ days. ### Exam Strategy & Shortcut Instead of fractions, you can use the LCM method for total work. Total Work = LCM of 96 hours and 80 hours = 480 units. Efficiency of P = $\frac{480}{96} = 5$ units/hr. Efficiency of Q = $\frac{480}{80} = 6$ units/hr. Combined efficiency = $5 + 6 = 11$ units/hr. Total time required = $\frac{480}{11}$ hours. Working 8 hours a day, days required = $\frac{480}{11} \div 8 = \frac{60}{11} = 5 \frac{5}{11}$. ### Common Pitfall A common error is trying to average the days or forgetting to standardize the time into hours before adding their work rates. Rates can only be added when the units are the same. ### Final Answer Therefore, the correct answer is **$5 \frac{5}{11}$**.
Discussion & Comments
No comments yet. Be the first to comment!