A job is planned for 36 men to finish in 48 days. After 24 days, only 2/5 of the work is completed. How many additional men must be employed so that the work is still finished within the original 48-day schedule?

Difficulty: Medium

Correct Answer: 18

Explanation:


Introduction / Context:
When progress lags behind schedule, we can increase the workforce to meet the deadline. We compare required man-days with what remains to determine the additional men needed.


Given Data / Assumptions:

  • Planned crew = 36 men for 48 days.
  • After 24 days, only 2/5 of the work is done.
  • Goal: finish by day 48 (24 more days).


Concept / Approach:
Total work can be expressed in man-days. Using progress data, infer the project’s true size, then compute remaining man-days and divide by remaining days to get the required headcount.


Step-by-Step Solution:

Planned production in 24 days = 36 * 24 = 864 man-daysBut this equals 2/5 of actual work → Total work = 864 * (5/2) = 2160 man-daysWork done = 864, Remaining = 2160 - 864 = 1296 man-daysDays left = 48 - 24 = 24 daysRequired men = 1296 / 24 = 54 menAdditional men = 54 - 36 = 18


Verification / Alternative check:
54 men * 24 days = 1296 man-days remaining; matches need exactly.


Why Other Options Are Wrong:

  • 16, 14: Under-hire; would miss deadline.
  • 20, 22: Over-hire; more than necessary given exact calculation.


Common Pitfalls:
Using planned total (36*48) as actual work without adjusting for the slower-than-expected progress; forgetting to subtract completed man-days before computing requirements.


Final Answer:
18

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion