Six men can finish a work in 12 days; eight women can finish it in 18 days; and eighteen children can finish it in 10 days. First, 4 men, 12 women, and 20 children work together for 2 days. If only men must finish the remaining work in 1 additional day, how many men are required?

Difficulty: Medium

Correct Answer: 36

Explanation:


Introduction / Context:
Convert each group's capability into an equivalent daily rate per individual, then add contributions over the first phase. The remainder is completed by men in a final 1-day push.


Given Data / Assumptions:

  • 6 men → 12 days → 72 man-days → 1 man = 1/72 per day.
  • 8 women → 18 days → 144 woman-days → 1 woman = 1/144 per day.
  • 18 children → 10 days → 180 child-days → 1 child = 1/180 per day.


Concept / Approach:
Compute the fraction of work done in first 2 days, then set n*(1/72) = remaining work (to be done in 1 day) to find n.


Step-by-Step Solution:

Daily combined rate = 4*(1/72) + 12*(1/144) + 20*(1/180)= 1/18 + 1/12 + 1/9 = 1/4 per dayWork in 2 days = 1/2; Remaining = 1/2Let required men = n; In 1 day: n*(1/72) = 1/2 → n = 36


Verification / Alternative check:
Cross-check equivalences: woman = 1/144 = half of man; child ≈ 0.4 of man; totals align to 1/4 per day.


Why Other Options Are Wrong:
Undershoot or overshoot the exact half-work remaining within a single day.


Common Pitfalls:
Arithmetic slips when summing heterogeneous rates; forgetting that the final phase is only 1 day.


Final Answer:
36

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion