Difficulty: Medium
Correct Answer: 7 1/7 days
Explanation:
Introduction / Context:Time-and-work problems often adjust worker efficiencies due to constraints like illness or fatigue. Here, A and B do not work at full capacity, so we must scale their normal rates and then combine the reduced rates to find the total time.
Given Data / Assumptions:
Concept / Approach:Convert times to rates, scale by efficiency, add rates to get the combined rate, then invert to get total time. Use rate = 1 / time. Multiply rates by the efficiency fraction when efficiency is reduced.
Step-by-Step Solution:
A's usual rate = 1/9 per dayA's reduced rate = 0.90 * (1/9) = 1/10B's usual rate = 1/18 per dayB's reduced rate = 0.72 * (1/18) = 0.04 = 1/25Combined reduced rate = 1/10 + 1/25 = (5 + 2)/50 = 7/50 per dayTotal time = 1 / (7/50) = 50/7 days = 7 1/7 daysVerification / Alternative check:Approximate: If both worked at full efficiency, time would be 1 / (1/9 + 1/18) = 6 days. Reduced efficiencies should increase time above 6; 7.14 days is reasonable.
Why Other Options Are Wrong:
Common Pitfalls:Using reduced time instead of reduced rate; forgetting to scale each person's rate by the efficiency percentage; adding times directly instead of rates.
Final Answer:7 1/7 days
Discussion & Comments