Difficulty: Medium
Correct Answer: 7 1/7 days
Explanation:
Introduction / Context:
Time-and-work problems often adjust worker efficiencies due to constraints like illness or fatigue. Here, A and B do not work at full capacity, so we must scale their normal rates and then combine the reduced rates to find the total time.
Given Data / Assumptions:
Concept / Approach:
Convert times to rates, scale by efficiency, add rates to get the combined rate, then invert to get total time. Use rate = 1 / time. Multiply rates by the efficiency fraction when efficiency is reduced.
Step-by-Step Solution:
Verification / Alternative check:
Approximate: If both worked at full efficiency, time would be 1 / (1/9 + 1/18) = 6 days. Reduced efficiencies should increase time above 6; 7.14 days is reasonable.
Why Other Options Are Wrong:
Common Pitfalls:
Using reduced time instead of reduced rate; forgetting to scale each person's rate by the efficiency percentage; adding times directly instead of rates.
Final Answer:
7 1/7 days
Discussion & Comments