Sometimes project managers forget all of the expenses that they can incur on a project, such as capital resources and assets. This can have an impact upon their budgets and the economic return on the project. A cost that has been incurred and cannot be reversed is known as a

Certification PMP Certification
Choose an option
  • A
    Fixed Cost
  • B
    Direct Cost
  • C
    Variable Cost
  • D
    Sunk Cost

Answer

Correct Answer: Sunk Cost

Explanation

Answer D is correct because a sunk cost is a project expense that will eventualy need to be paid. Answer A is incorrect because a fixed cost remains constant, regardless of any change in a company's activity. Answer B is incorrect because direct cost can be directly linked to producing specific goods or services. Answer C is incorrect because a variable cost changes in proportion to a change in the company's activity or business.