Difficulty: Easy
Correct Answer: 13
Explanation:
Introduction / Context:
The quantity of work is proportional to total man-hours = persons * hours/day * days. If the work is the same, equate the man-hours of the two scenarios and solve for the unknown number of days in the second scenario. This is a direct application of the unitary method for work-rate problems.
Given Data / Assumptions:
Concept / Approach:
Man-hours A = Man-hours B ⇒ 39*12*5 = 30*D*6. Solve for D algebraically. Avoid canceling prematurely to prevent arithmetic slips.
Step-by-Step Solution:
Verification / Alternative check:
Back-check: 30*6*13 = 2340 man-hours, which equals the original requirement, so the same work is completed.
Why Other Options Are Wrong:
Common Pitfalls:
Confusing proportionality (fewer workers at more hours) or dropping a factor of hours/day. Always compute total man-hours explicitly.
Final Answer:
13
Discussion & Comments