Difficulty: Easy
Correct Answer: 9
Explanation:
Introduction / Context:
This is a proportional scaling of man-hours with a changed team size and target workload (twice the original). We equate required man-hours using the same per hour productivity and solve for the daily hours needed in the new scenario.
Given Data / Assumptions:
Concept / Approach:
Man-hours scale linearly with workload. Therefore, 9*12*5 corresponds to W; for 2W, we require twice that many examiner-hours distributed as 4*30*H. Solve for H.
Step-by-Step Solution:
Verification / Alternative check:
Back-check: 4 * 30 * 9 = 1080 man-hours, exactly double the original 540, so twice the workload is feasible in 30 days.
Why Other Options Are Wrong:
Common Pitfalls:
Forgetting to double the original workload; or equating 9*12*5 directly to 4*30*H without the factor of 2, which would understate hours/day.
Final Answer:
9
Discussion & Comments