Difficulty: Easy
Correct Answer: 6
Explanation:
Introduction / Context:
For constant efficiency, work done equals total man-hours. We use the first scenario to get the total man-hours required, and then solve for the daily hours in the second scenario so that the man-hours match the same total work.
Given Data / Assumptions:
Concept / Approach:
Equate man-hours required: 10*6*18 = 15*H*12. Solve for H (hours/day) algebraically. This is the standard unitary-method application in work-rate problems.
Step-by-Step Solution:
Verification / Alternative check:
Back-check: 15 * 6 * 12 = 1080, same as Scenario A, so the job can be finished in the new schedule with 6 hours/day.
Why Other Options Are Wrong:
Common Pitfalls:
Forgetting to multiply by days, or mis-canceling factors when solving the proportion. Keep all factors visible until the final step.
Final Answer:
6
Discussion & Comments