Difficulty: Easy
Correct Answer: 49
Explanation:
Introduction / Context:
This is a classic unitary-method (work–time) question. For similar work, total output is directly proportional to the product men * days, assuming all men work at the same constant rate. We use this proportionality to scale from one scenario to another.
Given Data / Assumptions:
Concept / Approach:
Total work (length of wall) ∝ men * days. Hence, length2 = length1 * (men2 * days2) / (men1 * days1). Compute once and select the matching option.
Step-by-Step Solution:
Verification / Alternative check:
Use direct ratio: length2 = 56 * (35*3)/(20*6) = 56 * 105 / 120 = 56 * 0.875 = 49 m. Same result via either method.
Why Other Options Are Wrong:
Common Pitfalls:
Dividing by the wrong base (e.g., scaling by men only and forgetting days) or assuming inverse proportion. Here, output grows with both men and days.
Final Answer:
Discussion & Comments