Industrial Engineering and Production Management problems


  • 1. The correct sequence of phases in value engineering is

  • Options
  • A. creative phase, information phase, investigation phase, evaluation phase
  • B. information phase, creative phase, investigation phase, evaluation phase
  • C. investigation phase, information phase, creative phase, evaluation phase
  • D. creative phase, investigation phase, evaluation phase, information phase
  • Discuss
  • 2. Micromotion study is

  • Options
  • A. analysis of one stage of motion chart
  • B. motion study, when seen on a time chart
  • C. subdivision of an operation into therbligs and their analysis
  • D. enlarged view of motion study
  • Discuss
  • 3. Dummy activities are used to

  • Options
  • A. determine the critical path
  • B. determine the project completion time
  • C. maintain the required net work
  • D. none of these
  • Discuss
  • 4. The type of layout used for manufacturing steam turbines, is

  • Options
  • A. product layout
  • B. process layout
  • C. fixed position layout
  • D. any one of these
  • Discuss
  • 5. F. W. Taylor introduced a system of organisation known as

  • Options
  • A. line organisation
  • B. functional organisation
  • C. line and staff organisation
  • D. line, staff and functional organisation
  • Discuss
  • 6. Two alternatives can produce a product. First has a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is

  • Options
  • A. 25
  • B. 50
  • C. 75
  • D. 100
  • Discuss
  • 7. The planning and scheduling of job order manufacturing differ from planning and scheduling of mass production manufacturing.

  • Options
  • A. Correct
  • B. Incorrect
  • Discuss
  • 8. An event is a function of two or more activities.

  • Options
  • A. Correct
  • B. Incorrect
  • Discuss
  • 9. Product layout is best suited where

  • Options
  • A. one type of product is produced
  • B. product is standardised
  • C. product is manufactured in large quantities
  • D. all of the above
  • Discuss
  • 10. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

  • Options
  • A. 0.50
  • B. 0.66
  • C. 0.84
  • D. 0.95
  • Discuss