CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Industrial Engineering and Production Management problems
1. Time study is carried out to determine the time required to complete job by
Options
A. a slow worker
B. a fast worker
C. an average worker
D. an apprentice
Show Answer
Scratch Pad
Discuss
Correct Answer: an average worker
2. A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT).
Options
A. Correct
B. Incorrect
Show Answer
Scratch Pad
Discuss
Correct Answer: Correct
3. In process layout
Options
A. handling and back-tracking of materials is too much
B. production control is more difficult and costly
C. routing and scheduling is more difficult
D. all of the above
Show Answer
Scratch Pad
Discuss
Correct Answer: all of the above
4. The most important function of inventory control is
Options
A. stock control system
B. to run the stores effectively
C. technical responsibility for the state of materials
D. all of the above
Show Answer
Scratch Pad
Discuss
Correct Answer: all of the above
5. A feasible solution to the linear programming problem should
Options
A. satisfy the problem constraints
B. optimise the objective function
C. satisfy the problem constraints and non-negativity restrictions
D. satisfy the non-negativity restrictions
Show Answer
Scratch Pad
Discuss
Correct Answer: satisfy the problem constraints and non-negativity restrictions
6. Generally PERT is preferred over CPM for the purpose of project evaluation.
Options
A. Yes
B. No
Show Answer
Scratch Pad
Discuss
Correct Answer: Yes
7. Service time in queuing theory is usually assumed to follow
Options
A. normal distribution
B. Poissons distribution
C. Erlang distribution
D. exponential law
Show Answer
Scratch Pad
Discuss
Correct Answer: exponential law
8. Time study is used to
Options
A. determine standard costs
B. determine the number of machines a person may run
C. provide a basis for setting piece price or incentive wages
D. all of the above
Show Answer
Scratch Pad
Discuss
Correct Answer: all of the above
9. PERT is applied for
Options
A. marketing programmes and advertising programmes
B. installation of machinery
C. research and development of products
D. all of these
Show Answer
Scratch Pad
Discuss
Correct Answer: all of these
10. Monte Carlo solution in queuing theory is extremely useful in queuing problems that can not be analysed mathematically.
Options
A. Agree
B. Disagree
Show Answer
Scratch Pad
Discuss
Correct Answer: Agree
First
13
14
15
...
..
16
Last
More in Mechanical Engineering:
Automobile Engineering
Compressors, Gas Dynamics and Gas Turbines
Engineering Materials
Engineering Mechanics
Heat Transfer, Refrigeration and Air Conditioning
Hydraulic Machines
Hydraulics and Fluid Mechanics
IC Engines and Nuclear Power Plants
Industrial Engineering and Production Management
Machine Design
Production Engineering
Steam Boilers and Engines
Steam Nozzles and Turbines
Strength of Materials
Theory of machines
Thermodynamics
Workshop Technology