Arrange the construction activities in a practical sequence: (a) Plastering (b) Painting (c) Foundation (d) Walls (e) Ceiling.

Verbal Reasoning Logical Sequence of Words Difficulty: Easy
Choose an option
  • A
    c, d, a, b, e
  • B
    a, b, c, d, e
  • C
    e, d, c, b, a
  • D
    c, d, e, a, b
  • E
    None of these

Answer

Correct Answer: c, d, e, a, b

Explanation

Introduction / Context:Construction follows a structural-to-finish flow.

Given Data / Assumptions:

  • Foundation → structural base.
  • Walls → main vertical structure.
  • Ceiling/Roof → overhead structure.
  • Plastering → finishing of surfaces.
  • Painting → final finish.

Concept / Approach:First erect structure, then finishes.

Step-by-Step Solution:Correct sequence: c → d → e → a → b.

Final Answer:c, d, e, a, b