Arrange the construction activities in a practical sequence: (a) Plastering (b) Painting (c) Foundation (d) Walls (e) Ceiling.

Difficulty: Easy

Correct Answer: c, d, e, a, b

Explanation:


Introduction / Context:
Construction follows a structural-to-finish flow.


Given Data / Assumptions:

  • Foundation → structural base.
  • Walls → main vertical structure.
  • Ceiling/Roof → overhead structure.
  • Plastering → finishing of surfaces.
  • Painting → final finish.


Concept / Approach:
First erect structure, then finishes.


Step-by-Step Solution:
Correct sequence: c → d → e → a → b.


Final Answer:
c, d, e, a, b

More Questions from Logical Sequence of Words

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion