Arrange the construction activities in a practical sequence: (a) Plastering (b) Painting (c) Foundation (d) Walls (e) Ceiling.

Difficulty: Easy

Correct Answer: c, d, e, a, b

Explanation:

Introduction / Context:Construction follows a structural-to-finish flow.

Given Data / Assumptions:

  • Foundation → structural base.
  • Walls → main vertical structure.
  • Ceiling/Roof → overhead structure.
  • Plastering → finishing of surfaces.
  • Painting → final finish.

Concept / Approach:First erect structure, then finishes.

Step-by-Step Solution:Correct sequence: c → d → e → a → b.

Final Answer:c, d, e, a, b