Arrange the construction activities in a practical sequence: (a) Plastering (b) Painting (c) Foundation (d) Walls (e) Ceiling.
Verbal Reasoning
Logical Sequence of Words
Difficulty: Easy
Choose an option
-
Ac, d, a, b, e
-
Ba, b, c, d, e
-
Ce, d, c, b, a
-
Dc, d, e, a, b
-
ENone of these
Answer
Correct Answer: c, d, e, a, b
Explanation
Introduction / Context:Construction follows a structural-to-finish flow.
Given Data / Assumptions:
- Foundation → structural base.
- Walls → main vertical structure.
- Ceiling/Roof → overhead structure.
- Plastering → finishing of surfaces.
- Painting → final finish.
Concept / Approach:First erect structure, then finishes.
Step-by-Step Solution:Correct sequence: c → d → e → a → b.
Final Answer:c, d, e, a, b