Difficulty: Easy
Correct Answer: You implement the new database.
Explanation:
Introduction / Context:Enterprise data modeling is a strategic planning activity that creates an organization-wide view of data. It precedes project-level design and physical implementation.
Given Data / Assumptions:
Concept / Approach:The enterprise model identifies subject areas, major entities, and integration points across departments. Activities include assessing current systems, defining high-level requirements, and planning downstream projects. Physical build and deployment occur after detailed design, not during enterprise modeling.
Step-by-Step Solution:
Check each option against strategic scope.Review current systems → strategic and valid.Describe high-level data → valid.Plan projects → valid output of the modeling stage.Implement database → outside enterprise modeling → incorrect.Verification / Alternative check:Methodologies place enterprise data modeling before logical/physical design and build phases.
Why Other Options Are Wrong:They are genuine activities of strategic analysis and planning.
Common Pitfalls:Blurring strategic and project execution phases; trying to implement before aligning enterprise semantics.
Final Answer:You implement the new database.
Discussion & Comments