Precise Levelling – IGA Recommendation for Probable Systematic Error
According to the International Geodetic Association (IGA) guidance for precise levelling, the probable systematic error in a levelling line of length k kilometers should not exceed which limit (units in millimetres)?
Open
View answer
Highway vs Railway – Ratio of Transition Curve Lengths for Same Radius
For a curve where full centrifugal ratio is developed and the allowable rate of gain of radial acceleration is 0.3 m/s^3, what is the ratio of the length of the transition curve (same radius) on a road to that on a railway?
Open
View answer
Astronomical Surveying – Convergence of True Meridians
Considering the earth’s geometry, how do true meridians at different longitudes behave as one moves from the equator toward the poles?
Open
View answer
Setting Out Simple Circular Curves with Two Theodolites – What Is Required?
When a simple circular curve is set out using two theodolites from the tangent points, which data are required to turn and lay out the points correctly?
Open
View answer
Plane Table Survey – When to Use the Two-Point Problem for Orientation
Orientation of a plane table by solving the two-point problem is preferably adopted under which field condition?
Open
View answer
Chaining Error – Effect of a Too-Short Chain on Measured Distance
If a 30 m chain is actually 0.01 m too short (i.e., its true length is 29.99 m) and is used for chaining, what type of error is introduced in the measured distance over a long line?
Open
View answer
Stepping on Uniform Slope – Approximate Error Magnitude
A uniform slope between two points was measured by the stepping method. If the vertical difference in level is 1.8 m and the single-slope (hypotenuse) distance is 15 m, what is the approximate error magnitude attributable to using the slope length instead of the true horizontal distance?
Open
View answer
Levelling on an Up Gradient – Limiting Sight Length with Staff and Instrument Height
In differential levelling, with instrument height 1.0 m above ground, staff length 4.0 m, and the ground rising at 1 in 10, what is the maximum permissible sight distance on the up slope so that the line of sight still intersects the staff scale (i.e., staff reading remains non-negative)?
Open
View answer
Rankine’s Method – Deflection Angle for Normal Chord on a 100 m Radius Curve
For a simple circular curve of radius R = 100 m and a normal chord length c = 10 m, what is the Rankine’s deflection angle (to the chord) from the tangent point?
Open
View answer
Surveying correction for area due to erroneous chain length
If the area of a plan has been computed from measurements taken with an erroneous chain (too long or too short), how should the accurate (true) area be obtained from the calculated area? Select the correct correction factor and relation.
Open
View answer
Traverse positional error from bearing uncertainty
If θ is the probable error (in radians) of the observed bearing of each line of length l, what is the probable position error at the end of a traverse of n equal lines (each of length l)? Assume independent random bearing errors.
Open
View answer
Metric chains used in chain surveying
Which standard lengths are metric chains generally available in for field measurements?
Open
View answer
Intervisibility across equal-elevation hilltops
Two hilltops A and B are 20 km apart and an intervening top C lies between them. If the highest (top) contour of all three hilltops has the same elevation value, the straight line of sight AB will most likely:
Open
View answer
Traverse adjustment method selection
If angular (direction) measurements in a traverse are significantly more precise than the linear (distance) measurements, which adjustment rule should be used to balance the traverse?
Open
View answer
Bubble tube sensitivity and radius
A level’s bubble tube has 2 mm division spacing and a desired sensitivity of 30 seconds of arc per division. What should be the radius of curvature of the bubble tube?
Open
View answer
Setting out circular curves: two-theodolite method
When a circular curve is set out by the two-theodolite method, which type of field measurements does the method primarily employ?
Open
View answer
Plane table plotting of inaccessible points
On a plane table, which method is used to plot the position of an inaccessible point when you can occupy two (or more) accessible stations with known plan positions?
Open
View answer
Constructional details of survey chains
Which of the following statements about a survey chain and its accessories is/are correct?
Open
View answer
Shape of the bubble tube surface
The longitudinal profile (surface) of a level’s bubble tube is designed to be which geometric curve?
Open
View answer
Highway and railway alignment – identifying an S-shaped transition
In geometric design and surveying terminology, the curve composed of two circular arcs of different radii whose centers lie on opposite sides of the curve (producing an S-shaped path) is known as:
Open
View answer