Project Procurement Management - Processes Describe the Inputs, Tools and Techniques , Outputs included in the Contract Closure?

Correct Answer: I Inputs Procurement management plan Contract management plan Contract documentation Contract closure procedure II Tools and Techniques Procurement audits Records management system III Outputs Closed contracts Organizational process assets (updates)