Change control management is utilized from the begining to the end of the project in order to keep it focused with an emphasis on the time and budget. Answer A is incorrect because change control management is not seperate from the other phases. Answer B is incorrect because the control plan must be throughout the other phases of a project. Its usage is not optional, and consistent utilization is imperative to managing scope creep and other scope expansions. Answer C is incorrect because the project sponsors is generally not responsible for the change control documentation, although it should be involved in the buy-in and approval process.