Difficulty: Medium
Correct Answer: 162
Explanation:
Introduction / Context:
Varying daily hours changes throughput, so compute in man-hours. From the completed fraction, determine the remaining man-hours and solve for the headcount at the new hours to meet the deadline.
Given Data / Assumptions:
Concept / Approach:
Let W be total man-hours. Use 66-day production to infer W, then compute men M such that M * 18 * 26 equals remaining 3/7 W. Subtract current 234 to get additional men.
Step-by-Step Solution:
Verification / Alternative check:
Dimensional check in man-hours confirms units and cancellation are consistent.
Why Other Options Are Wrong:
They do not satisfy the precise balance of remaining man-hours within 26 days at 18 h/day.
Common Pitfalls:
Using man-days instead of man-hours after changing daily hours.
Final Answer:
162
Discussion & Comments