Correct Answer: 12 days
Explanation:
(A + B)'s 1 day's work = | ❨ | 1 | + | 1 | ❩ | = | 1 | . |
15 | 10 | 6 |
Work done by A and B in 2 days = | ❨ | 1 | x 2 | ❩ | = | 1 | . |
6 | 3 |
Remaining work = | ❨ | 1 - | 1 | ❩ | = | 2 | . |
3 | 3 |
Now, | 1 | work is done by A in 1 day. |
15 |
∴ | 2 | work will be done by a in | ❨ | 15 x | 2 | ❩ | = 10 days. |
3 | 3 |
Hence, the total time taken = (10 + 2) = 12 days.