Home » Aptitude » Time and Work

A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?

Correct Answer: 18 days

Explanation:


2(A + B + C)'s 1 day's work = 1 + 1 + 1 = 15 = 1 .
30 24 20 120 8



Therefore, (A + B + C)'s 1 day's work = 1 = 1 .
2 x 8 16



Work done by A, B, C in 10 days = 10 = 5 .
16 8



Remaining work = 1 - 5 = 3 .
8 8



A's 1 day's work = 1 - 1 = 1 .
16 24 48



Now, 1 work is done by A in 1 day.
48



So, 3 work will be done by A in 48 x 3 = 18 days.
8 8


← Previous Question Next Question→

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion