Home » Aptitude » Time and Work

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

Correct Answer: 10 days

Explanation:


Work done by X in 4 days = 1 x 4 = 1 .
20 5



Remaining work = 1 - 1 = 4 .
5 5



(X + Y)'s 1 day's work = 1 + 1 = 8 = 2 .
20 12 60 15



Now, 2 work is done by X and Y in 1 day.
15



So, 4 work will be done by X and Y in 15 x 4 = 6 days.
5 2 5


Hence, total time taken = (6 + 4) days = 10 days.


← Previous Question Next Question→

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion