A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

Correct Answer: 8 15

Explanation:


A's 1 day's work = 1 ;
15



B's 1 day's work = 1 ;
20



(A + B)'s 1 day's work = 1 + 1 = 7 .
15 20 60



(A + B)'s 4 day's work = 7 x 4 = 7 .
60 15



Therefore, Remaining work = 1 - 7 = 8 .
15 15