Explanation:

Problem restatement
After 4 days of joint work, find the remaining fraction of the job.


Given data

  • A's time = 15 days → rate = 1/15.
  • B's time = 20 days → rate = 1/20.

Concept/Approach
Joint rate adds. Done in 4 days = 4 × (1/15 + 1/20). Remaining = 1 − (done).


Step-by-step calculation
Combined rate = 1/15 + 1/20 = (4 + 3)/60 = 7/60 Work done in 4 days = 4 × (7/60) = 28/60 = 7/15 Remaining fraction = 1 − 7/15 = 8/15


Verification
Convert to a common denominator if needed to avoid arithmetic slips.


Common pitfalls

  • Mistakenly averaging times (15 and 20) instead of adding rates.

Final Answer
8/15