Difficulty: Easy
Correct Answer: 8/15
Explanation:
Problem restatement
After 4 days of joint work, find the remaining fraction of the job.
Given data
Concept/Approach
Joint rate adds. Done in 4 days = 4 × (1/15 + 1/20). Remaining = 1 − (done).
Step-by-step calculation
Combined rate = 1/15 + 1/20 = (4 + 3)/60 = 7/60 Work done in 4 days = 4 × (7/60) = 28/60 = 7/15 Remaining fraction = 1 − 7/15 = 8/15
Verification
Convert to a common denominator if needed to avoid arithmetic slips.
Common pitfalls
Final Answer
8/15
Discussion & Comments