56 men can complete a piece of work in 24 days. In how many days can 42 men complete the same piece of work? (Bank P.O., 2008)
Aptitude
Time and Work
Difficulty: Easy
Choose an option
-
A18
-
B32
-
C48
-
D98
-
ENone of these
Answer
Correct Answer: 32
Explanation
### Concept & Man-Days Formula
The total amount of work can be measured in "man-days" (number of men multiplied by the number of days). For the same piece of work, the total man-days remains constant.
$$ M_1 \times D_1 = M_2 \times D_2 $$
### Step-by-Step Solution
* Given: $M_1 = 56$ men, $D_1 = 24$ days.
* Given: $M_2 = 42$ men, $D_2 = ?$ days.
* Total work = $56 \times 24$ man-days.
* Equate the total work to the second scenario: $56 \times 24 = 42 \times D_2$.
* Solve for $D_2$: $D_2 = \frac{56 \times 24}{42}$.
* Simplify the fraction: Divide 56 and 42 by 14 to get $\frac{4 \times 24}{3}$.
* Divide 24 by 3 to get 8.
* $D_2 = 4 \times 8 = 32$ days.
### Exam Strategy & Shortcut
Use the ratio method. The ratio of men is $56 : 42 = 4 : 3$. Since men and days are inversely proportional, the ratio of days will be $3 : 4$.
If 3 parts = 24 days, then 1 part = 8 days. So, 4 parts = $4 \times 8 = 32$ days.
### Common Pitfall
Setting up a direct proportion ($56/24 = 42/x$) instead of an inverse proportion, forgetting that fewer men will take *more* time, not less.
### Final Answer
Therefore, the correct answer is **32**.