30 men can do a piece of work in 16 days. How many men would be required to do the same work in 20 days? (Bank P.O., 2008)
Aptitude
Time and Work
Difficulty: Easy
Choose an option
-
A12
-
B24
-
C36
-
D48
-
ENone of these
Answer
Correct Answer: 24
Explanation
### Concept & Inverse Proportion in Work
The number of workers and the time required to complete a fixed amount of work are inversely proportional. The product of workers and time is constant.
$$ M_1 \times D_1 = M_2 \times D_2 $$
### Step-by-Step Solution
* Given: $M_1 = 30$ men, $D_1 = 16$ days.
* Given: $D_2 = 20$ days, $M_2 = ?$ men.
* Set up the equation based on total work: $30 \times 16 = M_2 \times 20$.
* Solve for $M_2$: $M_2 = \frac{30 \times 16}{20}$.
* Simplify the expression: Cancel the zeroes in 30 and 20 to get $\frac{3 \times 16}{2}$.
* $M_2 = 3 \times 8 = 24$ men.
### Exam Strategy & Shortcut
Look at the ratio of days: $16 : 20 = 4 : 5$. The ratio of men required will be the inverse, $5 : 4$.
If 5 parts = 30 men, then 1 part = 6 men. So, 4 parts = $4 \times 6 = 24$ men.
### Common Pitfall
Using direct proportion, leading to the incorrect assumption that more days requires more men. Always remember work equations use inverse proportionality.
### Final Answer
Therefore, the correct answer is **24**.