Difficulty: Medium
Correct Answer: 3313 days
Explanation:
Introduction / Context:Consolidation time estimates are essential for predicting settlement rates and scheduling construction. For one-dimensional primary consolidation, the nondimensional time factor Tv links elapsed time to the square of the drainage path length and coefficient of consolidation Cv.
Given Data / Assumptions:
Concept / Approach:
The fundamental relation is: t = Tv * Hdr² / Cv Convert the resulting minutes to days by dividing by 1440.
Step-by-Step Solution:
Compute Hdr² = 600² = 360000 cm².Using Tv = 0.20: t = 0.20 * 360000 / 0.015 = 4,800,000 min.Convert to days: 4,800,000 / 1440 ≈ 3333 days.If Tv = 0.197 (alternate table): t ≈ 4,728,000 min → 3283 days.Verification / Alternative check:
Both computations give roughly 3.3 × 10³ days. Among the provided discrete options, 3313 days is the closest realistic value and reflects small variations due to Tv rounding and field variability.
Why Other Options Are Wrong:
3123 and 3233 days deviate more from the 3283–3333 day band; “33331 days” appears to be a typographical error one order of magnitude too large; 2999 is too small for the given parameters.
Common Pitfalls:
Using total thickness instead of drainage path; mixing units (m vs cm); forgetting to convert minutes to days; misreading Tv from charts.
Final Answer:
3313 days