For earthwork in trenches or borrow pits, which statements correctly describe standard methods of measurement in uniform ground, irregular ground, and when direct methods are infeasible?
-
AIn fairly uniform ground, measure using average depths between dead men (reference pegs).
-
BIn irregular ground, determine quantities from the difference in levels before and after the work.
-
CWhere neither (a) nor (b) is feasible, measure from the filling quantities after deducting voids.
-
DAll the above.
-
EOnly (a) and (b).
Answer
Correct Answer: All the above.
Explanation
Introduction / Context:Earthwork measurement varies with site conditions. Surveyors select techniques that best reflect actual excavation or filling. Understanding when to use average depths (dead men), level differences, or filling-based back-calculation ensures fair and auditable quantities.
Given Data / Assumptions:
- Trenches or borrow pits can be in fairly uniform or irregular terrain.
- Dead men (reference pegs) mark original ground to gauge average depths easily.
- Filling-based inference is used only when direct measurement methods are impractical.
Concept / Approach:In uniform ground, average depths from fixed reference points give reliable volumes. In irregular ground, pre- and post-work levels yield volumetric differences. Where neither works (e.g., access constraints, waterlogged conditions), back-calculate from filled quantities and deduct voids to approximate the in-situ earthwork.
Step-by-Step Solution:Confirm A: Average depth method with dead men is standard for uniform ground.Confirm B: Level-difference (strip levels or grid) is appropriate for irregular ground.Confirm C: When direct measurement is infeasible, using fill with voids deduction is accepted practice.Hence D (All the above) is correct.
Verification / Alternative check:Field manuals outline all three as valid, with documentation of assumptions (e.g., bulking/void ratios) when using filling-based estimates.
Why Other Options Are Wrong:
- E omits the legitimate third contingency approach and is therefore incomplete.
Common Pitfalls:Ignoring bulking/compaction factors; using the average-depth method in highly irregular ground.
Final Answer:All the above.