Components at a canal–drain level crossing — identify the correct set of provisions typically adopted in a level crossing arrangement.

Difficulty: Medium

Correct Answer: All the above

Explanation:


Introduction / Context:
When a canal and a natural drain intersect at approximately the same bed level, a level crossing is adopted. Proper appurtenances are required to manage relative water levels and prevent undesirable backflows or sediment entry, while maintaining canal supply reliability.


Given Data / Assumptions:

  • Canal and drain cross at similar elevations.
  • No superpassage or aqueduct (i.e., no vertical separation).
  • Operational need to control flows on both channels near the junction.


Concept / Approach:

Standard practice provides (i) a crest/weir in the drain upstream of the junction to maintain adequate water level for controlled exchange, (ii) a regulator in the drain downstream to modulate outflows and prevent drawdown issues, and (iii) a cross-regulator on the canal downstream of the crossing to maintain canal F.S.L. and safeguard distribution.


Step-by-Step Solution:

At the drain upstream → install crest to stabilize approach level.At the drain downstream → regulator for controlled release and level management.On the canal downstream → cross-regulator to hold canal F.S.L. through the crossing.


Verification / Alternative check (if short method exists):

Operational simulations show that absence of any one element can cause level instability, reverse flows, or sediment ingress; the trio ensures robust control.


Why Other Options Are Wrong:

Any subset omits an essential control element; therefore, only “All the above” reflects the complete, typical provision set.


Common Pitfalls (misconceptions, mistakes):

Confusing level crossing with superpassage/aqueduct; forgetting the canal cross-regulator below the junction; ignoring sediment management after events.


Final Answer:

All the above

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion