Work-rate with unequal efficiencies: 10 men and 8 women together finish a job in 5 days. Given that one woman's daily work equals half of one man's daily work, in how many days will 4 men and 6 women complete the same job?

Difficulty: Easy

Correct Answer: 10 days

Explanation:


Introduction / Context:
This unitary-method problem tests conversion of mixed-efficiency teams to a common unit (e.g., “man-equivalents”) and then using rate * time = work. By expressing every worker's contribution in comparable terms, we can scale the time for any new team composition.


Given Data / Assumptions:

  • 10 men + 8 women finish the work in 5 days.
  • 1 woman does half the daily work of 1 man.
  • Find days needed by 4 men + 6 women to finish the same job.


Concept / Approach:
Let a man's daily rate be m units/day. Then a woman's daily rate is m/2. Convert each team to man-equivalents, compute the total work once, and reuse it to find the time for the second team.


Step-by-Step Solution:

Daily rate of (10 men + 8 women) = 10m + 8*(m/2) = 10m + 4m = 14m Total work W = (rate) * (time) = 14m * 5 = 70m Daily rate of (4 men + 6 women) = 4m + 6*(m/2) = 4m + 3m = 7m Required days = W / (new rate) = 70m / 7m = 10 days


Verification / Alternative check:
Because 4 men + 6 women is exactly half of the original team in man-equivalents (7m vs 14m), their time must double from 5 to 10 days. This proportionality check confirms the result.


Why Other Options Are Wrong:
9, 8 2/3, 11, 12 days do not preserve the rate-time inverse relationship between a 14m team and a 7m team for the same job size.


Common Pitfalls:
Forgetting that a woman works at m/2, or adding women as if they worked at rate m like men. Mixing up proportional reasoning is another frequent error.


Final Answer:
10 days

More Questions from Unitary Method

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion