Difficulty: Easy
Correct Answer: 10 days
Explanation:
Introduction / Context:This unitary-method problem tests conversion of mixed-efficiency teams to a common unit (e.g., “man-equivalents”) and then using rate * time = work. By expressing every worker's contribution in comparable terms, we can scale the time for any new team composition.
Given Data / Assumptions:
Concept / Approach:Let a man's daily rate be m units/day. Then a woman's daily rate is m/2. Convert each team to man-equivalents, compute the total work once, and reuse it to find the time for the second team.
Step-by-Step Solution:
Daily rate of (10 men + 8 women) = 10m + 8*(m/2) = 10m + 4m = 14m Total work W = (rate) * (time) = 14m * 5 = 70m Daily rate of (4 men + 6 women) = 4m + 6*(m/2) = 4m + 3m = 7m Required days = W / (new rate) = 70m / 7m = 10 daysVerification / Alternative check:Because 4 men + 6 women is exactly half of the original team in man-equivalents (7m vs 14m), their time must double from 5 to 10 days. This proportionality check confirms the result.
Why Other Options Are Wrong:9, 8 2/3, 11, 12 days do not preserve the rate-time inverse relationship between a 14m team and a 7m team for the same job size.
Common Pitfalls:Forgetting that a woman works at m/2, or adding women as if they worked at rate m like men. Mixing up proportional reasoning is another frequent error.
Final Answer:10 days