Difficulty: Easy
Correct Answer: 32
Explanation:
Introduction / Context:Total work is proportional to men * hours/day * days when productivity per man-hour is constant. Equate total man-hours across scenarios to find the unknown time for the changed team and schedule.
Given Data / Assumptions:
Concept / Approach:Set man-hours equal: 16*7*48 = 14*12*D, then solve for D. This is a classic men–hours–days proportionality problem under the unitary method.
Step-by-Step Solution:
16*7*48 = 14*12*D Reduce by 14: (16*(7/14))*48 = 12*D ⇒ (16*0.5)*48 = 12D ⇒ 8*48 = 12D 384 = 12D ⇒ D = 32 daysVerification / Alternative check:Man-hours in scenario 1 = 16*7*48 = 5376; scenario 2 = 14*12*32 = 5376; equality confirmed.
Why Other Options Are Wrong:56, 38, 30, 28 do not satisfy the equal-man-hours relation for the same field.
Common Pitfalls:Multiplying or dividing the wrong factors or forgetting that increasing hours/day allows fewer days for the same total work.
Final Answer:32
Discussion & Comments