Difficulty: Medium
Correct Answer: 35
Explanation:
Introduction / Context:
When hours per day change mid-project, treat work in man-hours. Use completed fraction to infer total work, then determine the remaining workforce at new hours to meet the deadline.
Given Data / Assumptions:
Concept / Approach:
Work W in man-hours. Compute W from the 2/5 completion, then solve M such that M*9*25 equals remaining 3/5 of W.
Step-by-Step Solution:
Verification / Alternative check:
Check: 140*9*25 = 31500 → matches remaining workload.
Why Other Options Are Wrong:
Off-by-one choices (34, 36, 37) test arithmetic; only 35 satisfies the exact equality.
Common Pitfalls:
Forgetting to convert to man-hours after changing the daily hours.
Final Answer:
35
Discussion & Comments