PERT (Program Evaluation and Review Technique): time estimates basis Identify the time estimates used as the basis for PERT analysis. Select the correct option.

Difficulty: Easy

Correct Answer: All of these (optimistic, most likely, pessimistic)

Explanation:

Concept
PERT uses three-point estimates: optimistic (a), most likely (m), and pessimistic (b) to compute expected activity duration and variance for networks under uncertainty.


Final Answer
All of these (optimistic, most likely, pessimistic)