PERT (Program Evaluation and Review Technique): time estimates basis Identify the time estimates used as the basis for PERT analysis. Select the correct option.

Mechanical Engineering Industrial Engineering and Production Management Difficulty: Easy
Choose an option
  • A
    Optimistic time only
  • B
    Pessimistic time only
  • C
    Most likely time only
  • D
    All of these (optimistic, most likely, pessimistic)

Answer

Correct Answer: All of these (optimistic, most likely, pessimistic)

Explanation

ConceptPERT uses three-point estimates: optimistic (a), most likely (m), and pessimistic (b) to compute expected activity duration and variance for networks under uncertainty.

Final AnswerAll of these (optimistic, most likely, pessimistic)