PERT time estimates: how many estimates does PERT require for each activity? According to the PERT (Program Evaluation and Review Technique) approach, identify the number of time estimates used to model activity duration uncertainty. Choose the correct option.

Mechanical Engineering Industrial Engineering and Production Management Difficulty: Easy
Choose an option
  • A
    single time estimate
  • B
    double time estimate
  • C
    triple time estimate
  • D
    none of these

Answer

Correct Answer: triple time estimate

Explanation

ConceptPERT models activity duration uncertainty with three estimates: optimistic (a), most likely (m), and pessimistic (b). These combine to give the expected time and variance for network analysis.

Why tripleUsing three points better captures uncertainty than a single or double estimate, improving schedule risk analysis.

Final Answertriple time estimate