Project scheduling: interpretation of negative slack/float When an activity shows negative slack (negative float) in a network schedule, what does it indicate for the overall program status and resources? Choose the most accurate statement.

Mechanical Engineering Industrial Engineering and Production Management Difficulty: Easy
Choose an option
  • A
    Extra resources are available and project completion is not delayed
  • B
    The programme is behind schedule and additional resources are required to finish on time
  • C
    The activity is critical and any delay will delay the whole project
  • D
    All of the above

Answer

Correct Answer: The programme is behind schedule and additional resources are required to finish on time

Explanation

ConceptSlack (float) is the allowable delay of an activity without affecting project dates. Negative slack means the required finish date is earlier than the earliest achievable finish—indicating the schedule is already behind.

ImplicationsNegative float typically requires acceleration measures (e.g., crashing, fast-tracking, or allocating more resources) to meet deadlines.

Final AnswerThe programme is behind schedule and additional resources are required to finish on time