Production scheduling: Which factors must be considered when preparing a feasible and efficient schedule?

Difficulty: Easy

Correct Answer: all of these

Explanation:


Introduction / Context:
Production scheduling translates plans into executable shop-floor sequences. Effective schedules balance capacity, precedence, and standard times while honoring product design constraints. Ignoring any element leads to missed due dates or excessive WIP.


Given Data / Assumptions:

  • Known bills of materials and engineering drawings.
  • Route sheets specifying machine/process order.
  • Standard times determined via work measurement.


Concept / Approach:
Component design drives tolerances, required processes, and inspection. The route sheet encodes feasible sequences and eligible resources. Time standards allow loading, line balancing, due-date promise, and capacity checks. Together they enable backward/forward scheduling, dispatching rules, and realistic completion dates.


Step-by-Step Solution:

Validate process route against design specifications.Apply standard times to compute loads and start/finish windows.Sequence jobs with priority rules while respecting setups and capacities.


Verification / Alternative check:
Gantt charts and finite-capacity scheduling simulations confirm feasibility; KPIs like on-time delivery and queue lengths validate the plan.


Why Other Options Are Wrong:
Focusing on a single factor (e.g., machine availability) ignores precedence and timing detail, leading to infeasible schedules.


Common Pitfalls:
Using outdated route sheets; neglecting changeover times; relying on guessed times instead of measured standards.


Final Answer:
all of these

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion