Difficulty: Easy
Correct Answer: all of the above
Explanation:
Introduction / Context:
Work measurement establishes the time required by a qualified worker to perform a defined task at a specified performance level. Accurate standard times are foundational for planning, costing, and incentives, impacting competitiveness and customer service.
Given Data / Assumptions:
Concept / Approach:
Using time study, PMTS (e.g., MTM, MOST), or work sampling, analysts derive standard times. These drive capacity planning, line balancing, MRP scheduling, due-date quoting, labor cost estimates, and incentive plan calibration. Without valid standards, plans are unrealistic, incentives unfair, and quotes inaccurate.
Step-by-Step Solution:
Verification / Alternative check:
Compare scheduled capacity vs. actual throughput; variance reduction after implementing reliable standards validates the objective benefits.
Why Other Options Are Wrong:
Each listed benefit is genuine and complementary; none alone captures the main objective’s breadth. Option (e) is incorrect and contrary to best practice.
Common Pitfalls:
Using outdated standards; neglecting allowances; failing to keep standards synchronized with method changes.
Final Answer:
all of the above