Difficulty: Easy
Correct Answer: Correct
Explanation:
Introduction / Context:
Time is a central constraint in engineering projects. HDL efforts must balance feature set, performance, verification depth, and resource availability within a deadline. Recognizing schedule as a hard constraint drives scope control, risk mitigation, and staged delivery plans.
Given Data / Assumptions:
Concept / Approach:
Classic project management triangles emphasize time, cost, and scope/quality. In HDL work, schedule awareness leads to milestones (I/O freeze, RTL freeze, verification closure), buffer for integration risks, and prioritization of must-have features. Without explicit schedule control, late integration bugs and scope creep can derail delivery.
Step-by-Step Solution:
Verification / Alternative check:
Conduct periodic schedule risk reviews; if verification lag is detected, reevaluate features or add resources before the window closes.
Why Other Options Are Wrong:
“Incorrect” dismisses a foundational management reality. “Only budget matters” overlooks that time itself is costly. “Schedule is irrelevant with IP cores” is false—IP integration, licensing, and verification still consume time.
Common Pitfalls:
Overcommitting features; underestimating verification and timing closure; ignoring lab bottlenecks for bring-up.
Final Answer:
Correct