Difficulty: Medium
Correct Answer: None
Explanation:
Introduction / Context:This is a work–time problem converting varying workforce over time into total man-days. Once the total man-days for completion are known, we can compute the time if only the original crew worked throughout and compare with the target to find the delay.Given Data / Assumptions:
Concept / Approach:Total work W equals the sum of man-days used in the actual schedule. Then compute how long 100 men alone would take: time_alone = W / 100. The delay = time_alone − 40, if positive.Step-by-Step Solution:
Total work W = (100 men * 35 days) + (200 men * 5 days)= 3500 + 1000 = 4500 man-days.If only 100 men worked: time = 4500 / 100 = 45 days.Delay relative to 40-day target = 45 − 40 = 5 days late.Verification / Alternative check:Check proportionality: replacing the final 5 days of 100 men with 200 men adds 500 extra man-days, exactly the shortfall that would have caused a 5-day delay at 100 man-days/day.
Why Other Options Are Wrong:
Common Pitfalls:Forgetting that “additional 100 men” means total 200 in the last 5 days, or miscomputing total man-days. Always aggregate man-days and then divide by the constant crew size for alternative schedules.
Final Answer:
None
Discussion & Comments