Home Civil Engineering Construction Management Comments

  • Question
  • Critical Path Net Work helps an engineer


  • Options
  • A. to concentrate his attention on critical activities
  • B. to divert the resources from non-critical advanced activities to critical activities
  • C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
  • D. all the above.

  • Correct Answer
  • all the above. 


  • Construction Management problems


    Search Results


    • 1. Military organisation is known as

    • Options
    • A. line organisation
    • B. line and staff organisation
    • C. functional organisation
    • D. none of these.
    • Discuss
    • 2. Final technical authority of a project lies with

    • Options
    • A. Assistant Engineer
    • B. Executive Engineer
    • C. Superintending Engineer
    • D. Chief Engineer.
    • Discuss
    • 3. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

    • Options
    • A. duration
    • B. total flat
    • C. free float
    • D. interfering float.
    • Discuss
    • 4. Various activities of a project, are shown on bar charts by

    • Options
    • A. vertical lines
    • B. horizontal lines
    • C. dots
    • D. crosses.
    • Discuss
    • 5. Works costing less than Rs. 20,000 are treated as

    • Options
    • A. projects
    • B. major projects
    • C. minor projects
    • D. all the above.
    • Discuss
    • 6. Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following:

    • Options
    • A. 1. Pouring of Concrete
      2. Erection of form work
      3. Curing of concrete
      4. Removal of form work
    • B. 1. Erection of form work
      2. Pouring of concrete
      3. Curing of concrete
      4. Removal of form work
    • C. 1. Removal of form work
      2. Erection of form work
      3. Pouring of concrete
      4. Curing of concrete
    • D. 1. Pouring of concrete
      2. Curing of concrete
      3. Erection of form work
      4. Removal of form work
    • Discuss
    • 7. A CPM family includes

    • Options
    • A. CPA (Critical Path Analysis)
    • B. CPP (Critical Path Plotted)
    • C. MCE (Minimum Cost Expenditure)
    • D. CPS (Critical Path Scheduling)
    • E. All the above.
    • Discuss
    • 8. Pick up the correct statement from the following:

    • Options
    • A. The float may be positive, zero or negative
    • B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
    • C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project
    • D. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
    • E. All the above.
    • Discuss
    • 9. The performance of a specific task in CPM, is known

    • Options
    • A. Dummy
    • B. Event
    • C. Activity
    • D. Contract.
    • Discuss
    • 10. A dummy activity

    • Options
    • A. is artificially introduced
    • B. is represented by a dotted line
    • C. does not consume time
    • D. all the above.
    • Discuss