There is not necessarily a relationship between projects in a portfolio. Answer D is actually one of the goals of PROGRAM management. PMBOK Guide [1.4]
Answers A, B and D all result from effectively integrating the work of the project management process groups. PMBOK [4.0]
Answer A is incorect because it is not a correct statement and has nothing to do with ambiguous jurisdiction. Answer C is incorrect because ambiguous jurisdiction is not related to legal issues at a company. Answer D is incorrect because the statement is incorrect and is not related to ambiguous jurisdiction.
?Sensitivity analysis helps to determine which risks have the most potential impact on the project.?
Key elements in the procurement management plan are enumerated in this PMBOK section. [12.1.3.1]
Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it?s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance.
?Verify Scope is the process of formalizing acceptance of the completed project deliverables. Verifying scope includes reviewing deliverables with the customer or sponsor to ensure that they are completed satisfactorily and obtaining formal acceptance of deliverables by the customer or sponsor.? PMBOK [5.4]
Answers B and C belong to quality management, and answer D was formulated by Elizabeth Duffy and suggested that we all try to adjust our lives so that we have a dynamic balance (homeostasis) between challenge and relaxation. Kerstner, Chapter 18
The first phase in a project always has the greatest degree of uncertainty because at this point in time the product is the least well defined. PMBOK, See figure 2-2. [2.1.1]