Assuming that the phases in a project are concept, development, implementation and termination, which phase typically has the highest degree of uncertainty?

Correct Answer: Concept

Explanation:

The first phase in a project always has the greatest degree of uncertainty because at this point in time the product is the least well defined. PMBOK, See figure 2-2. [2.1.1]